Predecessors

In a workflow, tasks rarely exist in isolation. They are usually connected by dependencies that determine execution order.

Predecessors

Each task can reference one or more predecessor tasks.

  • A predecessor is a task that must reach a certain state (usually done, skipped, or cancelled) before the dependent task can activate.

  • The relationship is evaluated according to the task’s activation policy (All / Any).

Example:

  • Task: Manager Approval

  • Predecessors: Upload Invoice

  • Activation policy: All

→ Task becomes active once invoice upload is finished.

Last updated