Predecessors
In a workflow, tasks rarely exist in isolation. They are usually connected by dependencies that determine execution order.
Predecessors
Each task can reference one or more predecessor tasks.
A predecessor is a task that must reach a certain state (usually done, skipped, or cancelled) before the dependent task can activate.
The relationship is evaluated according to the task’s activation policy (All / Any).
Example:
Task: Manager Approval
Predecessors: Upload Invoice
Activation policy: All
→ Task becomes active once invoice upload is finished.